Joining swissporPIR Alu boards across a large roof area

PIR insulation

At a glance

On a long roof, joint alignment is particularly easy to check where two runs of swissporPIR Alu pass either side of a rooflight and meet again beyond its kerb. If the runs start at different angles, a wedge-shaped gap appears on the far side. Before cutting, establish a reference line across the bay, draw the joints and check the edge orientation on the first pair of boards. The manufacturer offers square FIT/GK, rebated LAP/SF and tongue-and-groove TAG/NuF edges. Each affects how cut pieces fit. A two-layer build-up also needs a separate joint layout for the upper course.

Tongue and groove on a swissporPIR Alu board with aluminium facing

Use two boards to establish laying direction

Bring two boards together on a level surface. With LAP, the upper lip of one rebate covers the lower lip of the next. TAG has a tongue that enters a groove, while FIT brings two flat edges together. Mark the direction in which boards are added with an arrow on the roof plan.

Why do rows drift apart at openings?

Before splitting the run at a rooflight, transfer the reference line to the far side. Check the distance from the line to the board edges on both sides of the kerb. A misaligned first board can still be adjusted without lifting the entire strip.

The manufacturer declares a thermal conductivity of 0.022 W/(m·K) for swissporPIR Alu. A visible gap between boards is a local break in the insulation. Before covering it, determine whether the cause is a skewed row, a broken edge or debris caught in the profile.

Which edge should survive the cut?

At the kerb, mark the side that will face the adjacent full board. Retain the matching factory profile on that edge. Measure the cut in its actual location as an existing kerb may be out of square.

Write the dimensions and surviving edge orientation on each offcut. Two rectangles of equal width may have rebates facing opposite ways. A trial fit against the adjoining board will show whether a piece can be used at the next opening.

How to set out the second layer

Before concealing the lower course, sketch its joints with dimensions from a fixed point. On a second drawing, stagger the upper boards so that joints in the two layers do not coincide. Check the pattern where the run divides around an opening as well.

At the end of each stage, photograph both layers where part of the lower one is still exposed. The image records the laying direction and joint offset. Where the design calls for joint tape, apply it after checking that the cores and facings fit together.

Supporting a short cut piece

On a profiled steel deck, check where the end of a cut board falls relative to the top flanges. Engaging the tongue and groove does not provide a bearing. The support detail must account for board thickness, deck profile and the position of the cut edge.

If the drawing leaves a narrow unsupported strip at the opening, review the cutting plan with the designer before laying further bays. Moving the start of a row can allow larger pieces on both sides of the kerb. Recheck the joint positions in the second layer after the change.

Coverage in the order schedule

Ask the supplier for coverage per pack for the specified format, edge and thickness. Add boards needed for the cutting list to the count of full boards laid intact. Confirm profiled-edge availability particularly when ordering thin insulation.

Split the list into bays between the building grid lines. Record the number and edge type of pieces carried forward into the next bay. The first bay then gives a measured basis for the allowance, avoiding repeated waste allowances for the same piece at successive rooflights.

Inspecting the row beyond the rooflight

Beyond the first rooflight, place a whole board against the two converging runs and compare its edge with the reference line. Inspect the joint along its length and the bearing at both ends. Once this junction fits, the cutting layout can be repeated at subsequent rooflights.

7 branches. Materials closer to your project.

  • SEROCK — Dzierżenin 34 E [mapa]
  • BŁONIE — ul. Sochaczewska 138A [mapa]
  • RADOM — ul. Grobickiego 8 [mapa]
  • ŁÓDŹ — Natolin 8 [mapa]
  • OLSZTYN — Barczewo, ul. Prosta 9 [mapa]
  • WROCŁAW — ul. Jerzmanowska 10C [mapa]
  • GORZÓW WLKP. — ul. Zielona 33/34 [mapa]
Mapa oddziałów: Olsztyn, Serock, Błonie, Łódź, Radom, Wrocław i Gorzów Wlkp.

Free quote

What to include in your enquiry

Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.

Read next