Utherm Roof BM on flat roofs: matching the facing to the waterproofing
PIR insulation
Utherm Roof BM has two different glass fleece facings. B identifies the bituminised face and M the mineral-coated face. Before opening further pallets on a large roof, the roofer should be able to point out on a section which face meets the substrate, which meets the first waterproofing layer and how each junction is formed. This requires a specification for the complete assembly, including the waterproofing and attachment method. Lay the first board beside the drawing and photograph the exposed facing. When another crew starts the next section, it will have a reference even after the packaging has gone.

In this guide
Locating faces B and M on the roof section
List both facings in their specified order from the deck to the roof surface. Against each face, enter the material it will touch. At delivery, check the board designation against the section specified for that roof area.
Thickness and declared resistance of Roof BM
In Unilin’s data sheet, the declared thermal conductivity of Roof BM varies with thickness. It is 0.027 W/(m·K) below 80 mm, 0.026 from 80 mm to under 120 mm, and 0.024 from 120 mm upwards. Use the applicable band for each thickness being assessed.
The 100 mm board has a declared resistance of 3.80 m²K/W and the 120 mm board 5.00 m²K/W. The extra 20 mm therefore adds 1.20 m²K/W of board resistance. Check on the section that the extra height fits beneath the parapet flashing and at plant kerbs.
Board joints at a roof penetration
The 1,200 × 600 mm board has four square edges. Set out the pipe penetration in relation to the joints in adjacent rows. Check the actual sleeve position before cutting so pieces can be laid with continuous support around the opening.
Mark the cut pieces on either side of the sleeve on the layout. If the second piece needs a mirror-image shape, cut it with the required facing orientation in mind. Turning over a finished offcut would swap faces B and M.
The first waterproofing layer
Find the permitted substrate, attachment method and application conditions for the first layer in the waterproofing documentation. For bonding, check the named adhesive, moisture and temperature limits and surface preparation. A heat-applied method needs to be expressly specified for the chosen system.
Before covering, check the facing for moisture, dirt and damage along handling routes. Identify the boundaries of the corner and perimeter wind zones on the fixing plan. The crew starting the next membrane roll should know where the fixing specification changes.
Plant supports and fire documentation
For Roof BM, the manufacturer declares at least 150 kPa in compression at 10% deformation. To check plant supports, give the designer the load, foot dimensions and load-distributing layers. How long the insulation will carry that load also matters.
Reaction to fire class F applies to the Roof BM product. Keep the required classification for the complete roof on file, with the deck, layers and attachment covered by the document. Check its scope again if the waterproofing is changed.
Pricing a complete roof area
Split the take-off into the main roof area, parapet perimeter and service penetrations. Add the materials and labour for the first waterproofing layer to the board quantities. Two quotations can then be compared for the same area and number of details.
Record the selected BM thickness and the waterproofing reference on the order. If an alternative board is offered, compare the facings, the figures for that thickness and the jointing instructions. Issue any agreed change to both crews before unloading.
Handing over a partly completed roof
If a shift stops halfway along a row, mark the last inspected board on a sketch and note whether the first waterproofing layer is in place. At restart, compare the exposed face of the next board with the reference photograph and check the temporary protection at the open edge.
Free quote
What to include in your enquiry
Tell us how you plan to use the material, the dimensions and the quantity you need. Include the thickness, grade or variant name, along with the delivery town or your preferred collection branch. For a specific product, add its name or a link to the product page. We will reply to the email address you provide to discuss availability and the terms of your order.
Read next
Divide the roof into the open field and the services strip before choosing an EFIGREEN ALU+ XL board size. Full boards fit…
On a large order, a small discrepancy in the board specification can affect an entire delivery. Specify the PIR facing, dimensions and…
The withdrawal of a sprout suppressant formerly used in potato stores changed storage practices. Residues in older buildings need separate assessment even…
A flat roof consists of several layers that work together. The structure carries the loads, insulation reduces heat loss and waterproofing keeps…
Choosing between PIR and mineral wool in an industrial or commercial building starts with three separate questions. How much thermal resistance is…
In a passive house, the roof is part of a continuous envelope around the heated rooms. Draw that boundary in section and…
Mark where the insulation sits on a roof section before choosing the material. Between irregular rafters, the priority may be a close…
Harvest sets the deadline for work on a potato store. Allow time to assess the building, order materials, install them and test…