Receiving and inspecting swissporPIR Alu deliveries on a large project
When swissporPIR Alu arrives for several industrial buildings, assign each pallet to a specific work area before lifting it to the roof. Match the label to the order, inspect the corners and underside of the pack, then mark the storage location on the plan. A damaged pack can then be isolated, documented and replaced without interrupting work elsewhere. Delivery order also depends on how many boards the crew can install and protect from rain. The following checks follow a pallet from unloading and storage to the inspection before the insulation is covered.